2026-W27
29 Jun 2026 to 5 Jul 2026
3 claims: 0 CONFIRMED, 3 UNCONFIRMED
Grouped by the site stated in the claim; moves use their destination. No site means no site was stated. A claim naming several vehicles or hardware items appears once under a combined group.
lc39a LC-39A
Site and other claims
note UNCONFIRMED
As of early July 2026, NSF reports LC-39A chopsticks are reeved so they can move on the tower, and ridge-cap and bucket deluge testing has begun.
slc37 SLC-37
Site and other claims
note UNCONFIRMED
As of early July 2026, NSF reports the SLC-37A tower had four of nine modules stacked, the flame trench was fully excavated, and rebar for the trench floor was underway.
gigabay-fl Gigabay (Florida)
Site and other claims
note UNCONFIRMED
As of early July 2026, NSF reports the Gigabay at Roberts Road has finished structural steel with cladding and roof nearly complete; both smaller doors are installed and the two large rollout doors are still in progress.